Carnarvon Bore Main Replacement Stage 1 & 22018-08-07T20:07:09+08:00

Project Description

Scope of Works

Fabrication, supply, pre-assembly, hydrostatic testing, protective wrapping, delivery and document of the underground DN600 and DN700 MSCL scour and air spools, tie-in connections, site consumables, safety bollards, DI fittings and equipment for the new water mains project to improve water supply to the Shire of Carnarvon.

Added Value: Spool assembly, hydrostatic testing, wrapping of flange connection for corrosion protection all completed at our Wangara facility to save time and reduce site installation costs.

Details

PROJECT

Carnarvon Bore Main Replacement Stage 1 & 2

CLIENT

Cape – Water Corporation

Gallery

Back to Projects